The 2024 loss of the Çanakkale Bridge has been revealed! A staggering figure...
It has been learned that 281 million euros were paid in 2024 for the Çanakkale Bridge, which was built using the Build-Operate-Transfer model.
12punto
The losses from bridges and highways built under the Build-Operate-Transfer model, which include traffic guarantees, continue to be covered by the Treasury.
Republican People's Party (CHP) Zonguldak Deputy Deniz Yavuzyılmaz shared striking data regarding the Çanakkale Bridge.
Stating that the error margin for the bridge is 84 percent, Yavuzyılmaz announced the 2024 loss report of the Çanakkale Bridge, built under the AKP's Build-Operate-Transfer model, in a post on his social media account.
ERROR MARGIN IS 84 PERCENT
Yavuzyılmaz explained the financial burden created by the bridge as follows:
"The 2024 loss report for the Çanakkale Bridge, built under the AK Party-style Build-Operate-Transfer model, has been released. In 2024, the guaranteed number of vehicle crossings: 16,425,000. The actual number of vehicle crossings: 2,684,738. Error margin: 84%. The guarantee amount paid by the Treasury to the company: 281,675,371 Euros. 281 Million Euros!"
The 2024 loss report for the Çanakkale Bridge, built under the AK Party-style Build-Operate-Transfer model, has been released.
— Deniz Yavuzyılmaz (@yavuzyilmazd) January 4, 2025
In 2024??
Guaranteed number of vehicle crossings:
16,425,000
Actual number of vehicle crossings:
2,684,738
Error margin:
84%
Guarantee amount paid by the Treasury to the company:
281,675,371… pic.twitter.com/7mPZ7ZHNEg