A positive EIA report has been issued for the copper mine project in Maden, Elazığ, by Eti Bakır, a subsidiary of Cengiz Holding. The project will affect an area the size of 409 football fields, and tree felling will be carried out on forest lands.
12punto
A positive Environmental Impact Assessment (EIA) report has been issued for the copper mine project to be carried out in Maden, Elazığ, by Eti Bakır, a subsidiary of Cengiz Holding, a company frequently mentioned in public tenders and owned by Mehmet Cengiz.
According to a report by Cumhuriyet, the document submitted by the company to the ministry shows that the project will affect an area of 290.81 hectares (approximately 409 football fields). The project site has been planned to encompass treasury, forest, agricultural, and private lands.
In addition to the underground copper mine to be established in the area, concrete plants, a pond, and an explosives storage facility will also be constructed.
While the ore is being extracted from underground, fill material will be provided from a previously permitted limestone quarry. The extracted ore will be enriched at a planned flotation plant and then sent to Eti Bakır's facilities in Samsun or Mazıdağı.
Forest Land Will Also Be Affected. The 5,022-page report prepared for the project states that the total cost of the project is 9 billion 10 million TL.
A total production of 32 million 885 thousand tons of ore is planned during the operations, which are expected to last 28 years.
A 2.5-hectare portion of the area where Eti Bakır will operate consists of forest land. The company calculated that there are 100 trees per hectare in this area and announced that 250 trees will be cut down as part of this scope.